Hazer Group Ltd (“Hazer” or “the Company”) (ASX: HZR) provide an update on the Company’s Commercial Demonstration Plant (“CDP”). The Company confirms that the CDP remains on schedule to commence Phase 2 of its operation (‘hot operations’), to produce hydrogen and graphitic carbon, in 2023.

Procurement activities have materially progressed further de-risking the start-up schedule:

  1. Following successful heat-treatment (ref. announcement 31st July 2023), the replacement heat
    exchanger has now been shipped to site and successfully installed at the CDP completing a
    significant milestone for the project as it approaches mechanical completion.
  2. The hot reactor main fabrication assembly is in the final stages, shortly enabling the commencement
    of final machining and heat treatment prior to delivery and installation, bringing remaining equipment
    procurement to a close

The reactor furnace has completed pre-commissioning checks and has been successfully energised to over 300 degrees Celsius in line with the initial testing procedures. Vendor confirmation was completed to further verify all systems are operating correctly, enabling a portion of the commissioning to be completed ahead of schedule.

The remaining hot piping fabrication being carried out by Callidus is also near completion and will be transported to the CDP for installation shortly.

Glenn Corrie, Hazer’s MD & CEO said:

We continue to make great progress in the final stages of our CDP completion and the installation of the replacement heat-exchanger is another significant milestone that materially de-risks the project schedule.

“Hazer has a critical role to play decarbonising global hard-to-abate industry with our advanced low-cost and game-changing technology. Our CDP is a key pillar in our commercialisation strategy demonstrating our technology on an industrial scale under continuous operation in readiness for commercial deployment, an exciting time for Hazer.”

ABOUT HAZER GROUP LTD

Hazer Group Limited (“Hazer” or “The Company”) is an ASX-listed technology development company undertaking the commercialisation of the Hazer Process, a low-emission hydrogen and graphitic carbon production process. The Hazer Process enables the effective conversion of natural gas and similar methane feedstocks, into hydrogen and high-quality advanced carbon materials, using iron ore as a process catalyst.

Highlights:

  • Heat exchanger (800HT) successfully installed at CDP
  • Reactor furnace commissioning commenced and successfully energised
  • Hot reactor (MKI) fabrication nearing completion
  • CDP remains on schedule

READ the latest news shaping the hydrogen market at Hydrogen Central

CDP ADVANCES AS HEAT EXCHANGER INSTALLED, PERTH, AUSTRALIA; August 31, 2023

Get our LinkedIn updates!

Join our weekly newsletter!

Follow us

Don't be shy, get in touch. We love meeting interesting people and making new friends.